NEW QUESTION 13
What is the difference between confirm and allocate actions?
- A. Confirm action creates hard allocation and allocate action creates soft allocation.
- B. Allocate action is always followed by confirm action.
- C. Confirm action creates soft allocation and allocate action creates hard allocation.
- D. They function the same way.
Answer: C
NEW QUESTION 14
At a minimum, which role is required to view the summary of a project in the Details tab of Project Workspace?
- A. it_project_user
- B. it_project_manager
- C. it_portfolio_manager
- D. itil
Answer: A
NEW QUESTION 15
Where do you define 'Roles' requested via resource plans?
- A. No need to define it differently, they are same are system roles
- B. Resource roles under resource management.
- C. Roles under system security
- D. Under skill management modules
Answer: B
NEW QUESTION 16
An it_pps_admin user is able to update: (Choose two.)
- A. Business Rules.
- B. Budget Periods.
- C. Client Scripts.
- D. Portfolio Targets.
Answer: B,D
NEW QUESTION 17
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)
- A. Demand.
- B. Project.
- C. Fixed Asset.
- D. Configuration Item (CI).
- E. User.
Answer: C,D,E
NEW QUESTION 18
Demand managers can enhance a demand request by adding the following: (Choose three.)
- A. Problems
- B. Decisions
- C. Requirements
- D. Stakeholders
- E. Change Requests
Answer: B,C,D
NEW QUESTION 19
In order for a business unit to have its own Idea Portal to retrieve data, what must be configured first?
- A. Idea module
- B. Idea Portal URL
- C. A business unit cannot have its own its own Idea Portal
- D. Idea categories
Answer: A
NEW QUESTION 20
What is the default schedule for a project?
- A. 8-hour workday (from 9 to 5).
- B. 8-hour workday (from 8 to 12 and 1 to 5).
- C. 8-hour workday (from 9 to 12 and 1 to 6).
- D. 9-hour workday (from 8 to 12 and from 1 to 5).
Answer: B
NEW QUESTION 21
Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?
- A. Any member and specific member.
- B. All members.
- C. Any member.
- D. Specific member.
Answer: C
NEW QUESTION 22
When entering time worked into a time sheet, which feature is recommended to group different types of work (e.g., standard hours and overtime)?
- A. Bill rate
- B. Category
- C. Rate type
- D. Rate model
Answer: C
NEW QUESTION 23
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Pending or Open, planned start date and planned end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Draft, actual start date and actual end date are displayed.
- D. If the project state is Work in Progress, actual start date and planned end date are displayed.
Answer: A,D
NEW QUESTION 24
If a user creates a new demand from the demand workbench, what state will the system save the record in?
- A. approved
- B. qualified
- C. open
- D. draft
Answer: B
NEW QUESTION 25
What role can create or modify a rate model?
- A. time_card_admin.
- B. release_admin.
- C. push_admin.
- D. it_pps_admin.
Answer: D
NEW QUESTION 26
When can a user choose from multiple rate types for their work, while logging a time card?
- A. Only if the capability is enabled in the Time Sheet Policies
- B. Only one (1) rate type can apply
- C. Only if the capability is enabled in the Project Preferences
- D. Only if this capability is enabled in the Project Record
Answer: A
NEW QUESTION 27
To set up a group for selection in a resource plan, the group record needs to include which role?
- A. pps_resource
- B. it_project_user
- C. resource_manager
- D. itil
Answer: A
NEW QUESTION 28
In the base system, what is the default number of cards that can be displayed in the project workspace?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D